What Rise Do You Get With An 18‰ Slope Over 750 m?
Permille slope means units of rise per 1,000 units of horizontal run. When the run is already in meters, the rise is a direct multiplication.
Interactive Rise Calculator
Enter slope as permille or percent, then choose a run distance to calculate rise directly.
Permille
Percent
Run Used
Worked Steps
- Use rise = (permille / 1,000) × run
- Substitute the values: (18 / 1,000) × 750
- 18 / 1,000 = 0.018
- 0.018 × 750 = 13.5
- So an 18‰ slope over 750 m rises 13.5 meters
FAQ
- What percent grade is 18‰?
1.8%. - How much rise is that per 100 meters?
1.8 meters of rise per 100 meters of run. - Do I need to convert meters to another unit first?
No. Because the run is already in meters, you can apply the formula directly.
Practical Context
How this exact question appears in real work and what the result helps you decide.
Example 1: Site And Drainage Checks
Who Asks This Question?
Civil and drainage teams ask what rise an 18‰ slope gives over 750 m when checking profiles and quick elevation changes. For this exact query: What rise do you get with an 18 permille slope over 750 meters?
What This Answer Tells You
The answer shows the segment rises 13.5 meters, which is the number needed for grade verification and layout review. For this case: Rise = 13.5 meters.
Example 2: Field Communication
Who Asks This Question?
Survey crews ask this exact 18 permille over 750 m question when turning a slope note into a more concrete elevation change on site. For this exact query: What rise do you get with an 18 permille slope over 750 meters?
What This Answer Tells You
Knowing the rise is 13.5 meters makes the gradient easier to explain during markups, checkpoints, and handoffs. For this case: Rise = 13.5 meters.